About Omiya campus floor switch replacement work

30/06/2018
About Omiya campus floor switch replacement work

During the summer season, Omiya campus will carry out the replacement work of the floor switch.

We apologize for the inconvenience. Thank you for your understanding.

Construction period:
August 9 - September 7, 2018
Construction contents:
Exchange work of network switches installed on each floor
  1. Removing wiring from the switch
  2. Switch change
  3. Label rewiring of wiring
  4. Connection of wiring to switch
  5. Confirm connection
Cautions:

During the work period, the network stops and the equipment using the network such as telephone, surveillance camera, classroom AV equipment, business terminal, multifunction machine, wireless LAN etc. cannot be used in the target area.

Each place is expected to stop for several hours.

Contact us:
Information service systems section

(Extension number : 5145/7530, goiken@sic.shibaura-it.ac.jp)

5. Work schedule
DateConstruction target school building and floor
8/9 University hall
8/10 Guard room
8/13 Building 2 1F
8/13 Building 6 1F・2F
8/14 Building 5 1F~5F office・Laboratory・Secretary room・Seminar room・Workshop room
8/14 Building 5 Building Extension 1F・2F
8/15 Building 5 Building Extension 3F・4F・5F
8/15~16 Building 4 3F・4F
8/16~17 Building 3 1F・2F
8/16~17 Building 4 5F
8/17~18 Tip building
8/17~18 Library
8/20~21 Building 3 3F・4F
8/21 Building 5 2F・3F classroom
8/21~22 Building 4 1F・2F
8/22 Building 5 4F classroom
8/22 Co-op
8/22 First gymnasium second gymnasium
8/23 Building 2 2F
8/23~24 Building 2 3F・4F
8/24 Saito Memorial Hall
8/24 Water disaster prevention experiment building
8/24 Animal care storage facility
8/24~25 First Club House
8/27~28 Second Club House
8/27~28 Tdird Club House
8/27~30 Building 2 B1F
8/30~9/4Building 5 1F PC classroom・5F PC classroom
9/5~6 Building 5 NOC1
9/7 Shibaura campus PC classroom